8. Planning
Planning Mode
Use Ready to Plan and Planned Assigned amounts to prepare category funding from scheduled inflows without changing actual assignments.
Use Planning Mode on the Budget page to decide what scheduled funding should cover. Plans record funding still intended for a category; assigning actual money fulfills that intention. Planning Mode is available when Scheduled Transactions is enabled and the month has planning available.
Switch between Actual and Planning modes #
The Budget summary shows the mode you are working in:
- Assign Mode shows Ready to Assign and edits Assigned. It is for real money that is available now.
- Planning Mode shows Ready to Plan and edits Planned Assigned. It is for allocating scheduled planning capacity, not spending or assigning actual cash.
Use the Ready to Plan summary card in the contextual sidebar to enter Planning Mode. Future months open directly in Planning Mode because they are forecasts; they do not offer normal Assigned editing. A month with an active pending cutover also keeps this future-style, planning-only view until you resolve the handoff through Review & Apply or Discard Plan. Otherwise, in a current month you can switch back with the Ready to Assign card.
Plan category funding #
In Planning Mode, enter a category’s Planned Assigned amount. In an ordinary current month this display includes the category’s Assigned amount plus its planned add-on; in a future month or during an active pending cutover it keeps the future-style planned amount for that month. Common Cents records the planned add-on separately from Assigned, so your live budget does not change just because you are looking ahead.
The planned add-on is the remaining funding you intend to assign. It is not an additional charge on top of a plan that has already been fulfilled. For example, $200 Assigned plus a $300 remaining plan means a total intention of $500; outside an active pending cutover, the current-month Planned Assigned field shows that combined $500.
If you manually enter a planned amount that exceeds the available planning capacity, Common Cents stops the change and asks you to add or adjust scheduled inflows first. Target actions work differently: they use the available capacity and can leave a category partially planned.
Understand Ready to Plan #
Ready to Plan (RTP) measures scheduled planning capacity after accounting for remaining and already fulfilled plans. Its calculation depends on whether the selected budget month is future or has an active pending cutover:
P = pending scheduled funding allocated to the month
R = received funding earmarked for the month
C = planned amounts already fulfilled through assignment
L = remaining planned amounts
S = P + R − C − L
Future month or active pending cutover RTP = S
Otherwise, current or past month RTP = min(P, S) For a future month, received earmarked funding remains planning capacity: that cash is reserved from an earlier month’s assignable money for the future month. An active pending cutover retains the same RTP calculation and planning-only view even after the calendar month changes. Review & Apply still uses actual available money during this handoff. Once the handoff is resolved, actual unassigned money belongs in Ready to Assign (RTA), not in a positive received-income surplus in RTP. Outside an active pending cutover, positive current/past RTP cannot exceed still-pending funding. Negative values of S remain visible as true planning shortfalls in either calculation; they are not clamped to zero.
This is planning capacity, not a second cash balance. Ready to Assign remains the authority for actual money you can assign now. Unrelated actual income does not independently increase RTP, and assigning money to a category with no remaining plan does not reduce RTP.
Creating or increasing pending scheduled funding can add planning capacity, as can received funding earmarked for a future month or a month with an active pending cutover. Increasing a remaining plan increases the commitment; reducing it releases that portion of the commitment. The formula above determines the effect on RTP: outside future months and active pending cutovers, realized current-month money cannot support an increase in positive RTP. Assigning against a plan does not release capacity: it changes the commitment from remaining to fulfilled.
Matching and funding months #
When an equal actual receipt is dated in or before the budget month it funds, matching changes the funding from pending to received without adding it a second time. For a future funding month or an active pending cutover, RTP stays unchanged because the received money remains earmarked planning capacity. Otherwise, for a current or past funding month, receiving the income can reduce positive RTP because pending funding falls and realized money does not supply positive RTP. For example, outside an active pending cutover, $500 pending with $300 committed leaves $200 RTP; receiving all $500 in the current month leaves $0 RTP, while actual unassigned money is available through RTA. Matching does not fulfill any category plan or resolve a pending handoff automatically.
If a receipt arrives in a later month than the one it was allocated to fund, it is not counted as received funding in that earlier month. Matching can therefore expose a shortfall there even when the amount is unchanged. Review the actual receipt date and funding allocation rather than assuming the earlier month’s forecast was met.
The budget month the inflow funds matters, not just the month you receive it. If September’s paycheck funds October while October is still future, it supports October’s RTP and is reserved from September’s assignable cash. When October becomes calendar-current, an active pending cutover keeps its planning capacity and planning-only view until the handoff is resolved. After resolution, or if no handoff is needed, its actual unassigned money belongs in RTA; any positive received surplus no longer appears in RTP. Money received in October but allocated to a still-future November supports November instead and is reserved from October’s assignable cash. October’s fulfilled plans stay associated with October.
When RTP is negative #
Negative RTP means remaining and fulfilled planning commitments exceed scheduled funding for that month. For example, if a $500 scheduled inflow ultimately arrives as $300, a $500 commitment has a $200 shortfall. RTP remains −$200 even if you use other actual cash to assign the full $500. The category can have actual money while its scheduled funding falls short.
Use View Funding Details to inspect pending inflows, received scheduled funding, Already funded from plan, and remaining Planned category funding. Reservations for later months explain excluded cash; they are not an additional deduction from the displayed month’s scheduled funding.
Assigning fulfills a plan #
Increasing Assigned in the grid and using Review & Apply follow the same rule: actual funding consumes the category’s remaining plan, up to the amount still planned. There is no need to subtract the plan yourself afterward. Direct Assigned editing is available only outside future months and active pending cutovers; successfully applying even part of a plan resolves the handoff and allows ordinary Assigned edits for any remaining plans.
Suppose $500 of still-pending scheduled funding is fully planned for one category and you have enough actual Ready to Assign from other cash. The scheduled $500 stays pending throughout this example; the actual cash used for assignment can be unrelated to that scheduled inflow:
| Action | Assigned | Remaining planned add-on | RTP |
|---|---|---|---|
| Plan $500 | $0 | $500 | $0 |
| Assign $200 | $200 | $300 | $0 |
| Increase Assigned to $600 | $600 | $0 | $0 |
| Reduce Assigned to $550 | $550 | $0 | $0 |
| Reduce Assigned to $400 | $400 | $100 | $0 |
| Reduce the remaining plan from $100 to $50 | $400 | $50 | $50 |
The $100 assigned beyond the original plan is extra funding. When Assigned decreases, extra funding is removed first. Only a further reduction of funding that fulfilled a plan restores planned dollars. Restoration keeps the commitment in place, so it does not independently increase RTP. To free that planning capacity, reduce the restored remaining plan.
Manually entered plans are fulfilled before target-generated plans. When a reduction restores fulfilled funding, target-generated amounts are restored before manual amounts, after any extra funding is removed.
Clearing or discarding remaining plans #
Setting a remaining plan to zero or choosing Discard Plan releases only the remaining planned amount. It does not unassign money or erase the fact that other planned dollars were already fulfilled. Reducing those assignments later can still restore their planned amounts. Undo/Redo restores the related assignment and plan changes together.
For example, with $500 of still-pending scheduled funding and $100 Assigned from a $500 plan using other actual cash, $400 remains planned. Clearing that remaining $400 releases $400 RTP, not $500; the fulfilled $100 stays committed. If the scheduled funding has instead been fully received for the current month and no active pending cutover remains, clearing the remaining plan still releases its commitment, but does not create positive RTP from that realized money. It can reduce a negative shortfall; any actual unassigned cash remains in RTA.
Resolve a plan at month cutover #
When a planned future month becomes the current calendar month, a pending handoff keeps it in the same future-style, planning-only view. An active pending cutover means all three conditions hold: the selected month is calendar-current, its saved handoff state is pending, and its total remaining plan is positive. Navigating to a month is not itself a calendar cutover. A month with no remaining plan has no forced handoff.
Resolve the handoff in one of two ways:
- Review & Apply: review actual available funding and successfully apply the selected amounts. Applying only some categories, or only part of their plans, is enough to mark the handoff reviewed and enter Assign Mode. Remaining plans stay intact and can then be fulfilled through ordinary Assigned edits or another review; they do not force another handoff just because they remain.
- Discard Plan: explicitly bypass the handoff by clearing the remaining plans. This preserves Assigned amounts and fulfilled-plan tracking; it does not unassign money or erase fulfilled commitments.
Receiving or matching scheduled income alone does not unlock Assign Mode. Review & Apply uses actual money even while the Budget remains planning-only. Canceling the review, or having no actual cash to apply, does not resolve the handoff.
After either resolution, RTP uses the ordinary current-month calculation, min(P, S). Resolving can therefore remove positive received surplus from RTP even though fulfilling a plan does not itself release its commitment. Undoing the resolving application or discard restores the pending handoff and planning-only view along with the related assignment and plan changes; redoing it resolves the handoff again.
Use targets in Planning Mode #
When Targets are enabled, Quick Plan in the sidebar fills category target needs from the top of the Budget grid downward. Group order comes first, then category order within each group. Put your highest planning priorities at the top.
Quick Plan uses the remaining planning capacity on the first category it cannot fully plan, rather than skipping it to plan a smaller target below. Once capacity reaches zero, later categories receive no new planned dollars. Search, filters, and collapsed groups do not narrow the action’s scope.
To plan only certain categories, select them and use Plan to Targets. It follows grid order, not selection order. For just one category, Plan up to target also uses the available capacity even when it cannot meet the full target need.
These actions preserve manually entered planned dollars. They recalculate the target-generated portion and can reduce it if less is now needed. Bulk planning applies those reductions first, then uses the released capacity for new planned dollars in grid order. It does not move an otherwise-needed plan from a lower category to a higher one just because you reordered them.
See Assigning Money for an example of full and partial funding.
Review the result before applying it: targets describe a goal, while Ready to Plan limits what the current forecast can support.
Keep planning and assigned funding separate #
Use Assigned to give actual money a category job. Use Planned Assigned to record the funding still intended for the category. Planning does not create actual money, and positive RTP does not override Ready to Assign’s cash limit.
Once actual funding is available in an editable month, use Review & Apply for a guided application across selected categories. Outside an active pending cutover, you can also increase Assigned by the amount you want to fund. Both fulfill remaining plans; neither requires a separate manual reduction of those plans.